Teach you how to do project development summary report
I introducer
1.1 Writing
Description Writing the purpose of this project development summary report indicates the expected reading range.
1.2 background
Description:
a. The name of this project and the name of the software system developed;
b. This software task makes a computing center for the developer, user, and install this software.
I. 3 definition
List the definitions of the specimen used in this document and the original phrase of the foreign letter group word.
1.4 Reference
List the references you want to use, such as:
a. The approved planned task book or contract of this project, the approval of the superior authority;
b. Other published files belonging to this item;
C. The documents, materials, information, including the software development criteria they want are included in this document. List the title, file number, publishing date, and publishing units of these files, indicating that the source of these files can be obtained.
2 actual development results
2.1 products
Description Finally made products, including:
a. The name of each program in the program system, the hierarchical relationship between them, the form and quantity of the storage media in the various programs of kilobytes;
b. Which versions of the program system have a total of their respective version numbers and their differences;
C. Name of each file;
d. Each database established. If the development of the configuration management plan is developed, it is necessary to compare with this plan.
2.2 Main functions and performance
One item lists the actual functionality and performance of this software product, which controls the feasibility study, project development plan, and functional needs. Ask for the content of the specification, indicating that the original development goal is reached, not fully reached, or more.
2.3 Basic Process
Use the figure to give the actual basic processing flow of the program system.
2.4 progress
List the comparison of the principal progress and actual progress, clearly stated that the actual progress is in advance, or is delayed, and the main reasons are analyzed.
2.5 fees
List the comparison of the cost of the original plan and actual expenses, including:
a. Timetime, in the month of the month, and statistics on different levels;
b. Computer usage time, difference CPU time and other equipment time;
C. Other expenditures such as material consumption, travel fees.
It is clear that the funds are exceeded, or it is sailed, and the main reasons are analyzed.
3 development work evaluation
3.1 Evaluation of Production Efficiency
Give actual production efficiency, including:
a. The average production efficiency of the program, that is, the number of rows produced per month;
b. The average production efficiency of the document is the thousand words produced by each month;
The original plan number is listed as contrast.
3.2 Evaluation of product quality
Note The error incidence in the program preparation inspected in the test, that is, the number of error instructions (or the number of statements) in each dry strip instruction (or statement). If the development of quality assurance plans or configuration management plans are developed in the development, they should be compared to these programs.
3.3 Evaluation of technical methods
A evaluation of the techniques, methods, tools, and means used in development is given.
3.4 Analysis of the cause of error
A reason to give the reason for the error occurring in the development.
4 experience and lesson
List the most important experience and lessons from this development work and recommendations for future project development work.