Based on .NET development and operational environment, architecture campus information system [5]

zhaozj2021-02-16  54

(Project Development Plan) [Part2]

III. Implementation Plan.

(1) Task decomposition.

Project task table

Task index number

Specific task

Developer

principal

Information database system

1

COM layer, DCOM layer

Web S Ervices layer

Student information service system

2

Teacher information entry system

Student wireless information service system

3

Student online test system

4

Information service system

5

Information AC terminal

(2) Progress arrangement. Http://members.lycos.co.uk/magicthink/thread_image.gif (3) Development cost budget.

Experts Li Estimate Total Number: 7000 Rows.

Expert Tianxin Estimated Code Total: 8200 rows.

Expert Lee Estimate Code Total: 7900 Row.

Average: NUM = (7300 8200 7900) / 3 = 7800 (line).

Cost Budget: TotalValue = 7800 Row * 10 RMB / Row = 78000 (RMB).

(4) Key questions.

1. The progress of the project is moderately controlled.

2. Design of information service system and information AC terminals based on SOAP.XML.

3. Database planning design.

5. Delivery period. December 18, 2002.

Six. Plan points.

1. Test plan (omitted). --------------------------------------- Statement ----------------------------------------

The document is written in the end of 2001 (Big Twenty), and the reference to the school's science and technology competition is written in accordance with SA. SD is limited by the level, the time is less expensive, the document is wrong and the deficiencies, please contact Magichink @ 163 .com ----------------------------------------------------------------------------------------------------------------------- ---------------------------------