Microsoft Solution Architecture (Module 6) (2)

zhaozj2021-02-17  50

4) How to build

I. Evolution to the plan

Transform the way to the plan

Find each team role responsible for planning input

Develop corresponding different quantities and complexity plans based on project characteristics

Don't confuse project plans and Project files

Ii. Program is a team event

Typical plan

Drive role

Communication plan

Product manager

Development Plan

Developer

training program

user experience

Security plan

Developers and release managers

Test Plan

Testers

Budget plan

Program manager

Deployment plan

Release manager

Purchase and Promotion Plan

Release manager and program manager

Trial operation plan

Release manager

2) When do you plan to generate?

I. Schedule

Use the duration of the task to estimate the created schedule

Including long vacation, short vacation and resources available

Ii. Schedule is a group activity

Each role group contributes to his own work contribution schedule information

Typical schedule

Drive role

Communication schedule

Product manager

Development schedule

Developer

Training schedule

user experience

Test schedule

Testers

Budget progress table

Program manager

Deployment schedule

Release manager

Purchase and promote progress table

Release manager and program manager

Trial operation schedule

Release manager

III. Suggestions for effective schedules

Apply risk-driven method to develop a schedule

Use the time box when appropriate

Keep the idea of ​​active on time

Arrange buffering time as a previous task of a primary milestone

IV. Synthetic and synchronization timetable

Solve the timetable conflicts between each role

Excessive resource

Unreasonable task arrangement relationship

Unreasonable or expired resource allocation

Program manager role creates a comprehensive project plan

Temporary milestone: The main project plan schedule is set up baseline

3) Prepare to develop and test the environment

I. Development and test environment

The development and test environment must be representative of the product environment

Isolation products, development and test environments are key

Ii. Prepare environment

Establish development and test environments

l Place the standard setting of the development and test plan

Consider logistics when generating and running development and testing environments

l Power and air conditioning

l Bandwidth and network access

l capacity

l Physical access and security

Iii. Establish and maintain a known situation

The development phase is only started after the baseline established for the development and test environment.

Implement configuration management and change control for tracking known shape

Synthetic development and test environment

IV. Review the milestone and delivery of the planning stage

Technical verification completion -> Customize the baseline of the specification -> Customized the baseline of the main project plan -> The baseline of the main project schedule is set -> The development and test environment has been established

Delivered product:

l Specification

l master project plan

l master project schedule

V. Standards for successful planning phase

Investors and teams agree on the following points:

l Solution Submit Component

l Key project milestone date

l How to generate

Development and test environment

The change control and configuration management process begins

Sponsor and key investors formally passed the commitments and get these entries

4) Summary of modules

The goal of the program phase is the architecture and design, project plan, schedule of the program.

Specifications are composed of detailed requirements, detailed scenes and design documents

Recommended estimation skills are discrete tasks with a downward estimate and allocation buffer time

For the program phase, submitted items are specifications, primary project plans, and master project time

转载请注明原文地址:https://www.9cbs.com/read-28667.html

New Post(0)