Police from the project and technicians participated in the joint project group.

During the implementation of the contract, the supervision and management of the project is directly responsible for the implementation of the project and provides the necessary cooperation and conditions.

Submit the necessary technical information to the joint project group, such as: Interface Specification, Power Environment (including UPS System Grounding) Test and Acceptance Report.

Ensure that the external conditions for the normal investment of networks have indeed already available. Such as: WANDE ports can work properly; the power environment between the equipment meets the requirements.

Party A technicians should be arranged from the joint project team in the implementation process of construction, participate in technical work and strive to learn about network technology and daily management maintenance.

The organization's acceptance of the network system and cooperated with Party B to submit the "Border Guard Network System Acceptance Report".

Fourth, the project implementation schedule

0 week

The two parties signed a contract, and B is submitted to Party A to participate in the list of joint project team.

1-3

Research and formulate "Engineering Implementation Plan", "Network Planning and Design", submitted to the leadership of both parties

4th week ago

Party A submits a network interface test situation, power environment and other technical specifications, guaranteeing its requirements

Day 6-8

Network equipment delivery, out the box;

Network technical training;

Network system installation and commissioning, application testing, submit "Engineering Implementation Report", "Network System Acceptance Report"

Last 10th week

Accepting the project acceptance of Party A, Party B provides all-day-sales service and technical support; provide toll-free domestic / foreign training as needed; further promotion of cooperation between the two parties

Note:

1. This timetable is based on the usual estimation. If there is an unpredictable situation, this timetable may change;

2. The comprehensive test of network system applications is based on the normal operation of other related soft / hardware products;

3. Cisco products provide faults within one year;

Five, Nan Tian project staff

Name Title Education Experience Technical Specialties Project Role Zhu Jianming Network Manager Shanghai Communication Student Impractive Bank City Network, CCB Maincraft Network Platform, Bank of Communications (National) Communication System, Great Wall Intelligent Building, Guangxi Bank Network System, Hainan Development Bank Communication System , Dongguan Postal Sales, Dongguan Telecom, Guilin ICBC Network, Nanhai Agricultural Credit, the original CCB Guangzhou Branch Network Reconstruction, Net Management Construction, CCB Guangdong Branch Network Reconstruction Project, etc. CCIe, large network construction, network communication programming, network implementation experience rich overall design, technical consultant, project is responsible Wang Yun network engineer Zhejiang University Bachelor degree Nanning, Liuzhou Bank of Communications Network System, Hainan Development Communication System, Dongguan Postal Sales, Nanhai Rural Credit Host system network construction, original construction line Guangzhou Branch Network transformation, network management construction, CCNA, Guangdong Branch Network Reconstruction Project CCNA, Familiar Network Management, Banking System Project Implementation Cai Shi Network Engineer Huazhong University of Science and Technology Bachelor degree Nanhai Rural Credit Host System Network Construction, Construction Bank Guangzhou Branch Network Transformation, Beihai ICBC Network Transformation, CCB Guangdong Branch Switch Upgrade, CCB Guangzhou Branch CallCenter. CCNA, CCNP is familiar with VoIP, ATM project implementation Zhou Wai network engineer Zhejiang University Mianyang City Telecom Network Engineering Construction, Zigong Telecom Network Engineering Construction, Xichang Satellite Launch Center Construction Familiar with Telecom Access Project Implementation