Project Development Summary Report (GB8567-88) (reproduced)

xiaoxiao2021-03-05  27

Project Development Summary Report (GB8567-88)

1 Introduction 1.1 Writing Description Writes the purpose of this project development summary report, pointing out the expected reading range.

1.2 Background Description:

a. The name of this project and the name of the software system developed;

b. This software task makes a computing center for the developer, user, and install this software.

1.3 Definitions list the definitions of the specimen used in this document and the original phrase of the foreign letter group word.

1.4 References List the references to be used, such as:

a. The approved planned task book or contract of this project, the approval of the superior authority;

b. Other published files belonging to this item;

C. The documents, materials, information, including the software development criteria they want are included in this document. List the title, file number, publishing date, and publishing units of these files, indicating that the source of these files can be obtained.

2 Real Development Results 2.1 Product Description Finally made products, including:

a. The name of each program in the program system, the hierarchical relationship between them, the form and quantity of the storage media in the various programs of kilobytes;

b. Which versions of the program system have a total of their respective version numbers and their differences;

C. Name of each file;

d. Each database established. If the development of the configuration management plan is developed, it is necessary to compare with this plan.

2.2 Main functions and performance item item item lists the actual functionality and performance of this software product, the relevant content of the feasibility study report, project development plan, functional requirements, indicating that the original development goal is achieved, not complete Reach, or more.

2.3 Basic flow Use the figure to give the actual basic processing flow of the program system.

2.4 Scientific Progress The comparison of the progress of the original plan and the actual progress, clearly stated that the actual progress is in advance, or is delayed, and the main reasons are analyzed.

2.5 Fees list comparisons for the original plan fees and actual expenses, including:

a. Work hours, in the monthly basis, and statistics on different levels;

b. Computer usage time, distinguish CPU time and other equipment time;

c. Other expenditures such as material consumption, travel fees.

It is clear that the funds are exceeded, or it is sailed, and the main reasons are analyzed.

3 Development Work Evaluation 3.1 The evaluation of production efficiency gives actual production efficiency, including:

a. The average production efficiency of the program, that is, the number of rows produced per month;

b. The average production efficiency of the document is the thousand words produced by each month;

The original plan number is listed as contrast.

3.2 Evaluation of Product Quality Description The error incidence in the program preparation inspected in the test, namely the number of error instructions (or the number of statements) in each dry strip instruction (or statement). If the development of quality assurance plans or configuration management plans are developed in the development, they should be compared to these programs.

3.3 Evaluation of technical methods gives the evaluation of the techniques, methods, tools and means used in the development.

3.4 Analysis of the cause of error given the cause analysis of errors in the development.

4 Experience and lessons list the most important experience and lessons from this development work and recommendations for future project development work.