Title: Direct Sa'an Administrative Center Monitoring System
Time: Mon Mar 7 23:25:36 2005
Click: 13
Engineering equipment: 4 infrared camera per layer in the 3 ~ 12th floor, 2 infrared camera, 2 infrared cinerazers per layer, basement, 13 ~ 16 floors, 4 infrared basements
Line camera
Basement 6 guns, 5 PTT, 5 guns
Five Anni hard drive video recorder, 220V turn 12V DC switch power supply 10
Project total quote: 195,000 yuan
Project is expected to cost: 80,000 yuan
Engineering Contractor: Lu'an Telecom Industrial Company (Project Leader / Chen Huai)
Secondary Contractor: Hefei WeClin Network Technology Co., Ltd. (General Manager / Li Changqi)
Finally, Understanding: Nanjing Maikang Network Technology Co., Ltd. (General Manager / Ningao)
Executive Engineering: Qin Hao (Nanjing Maikang Network Technology Co., Ltd. / Savet / Part-time Technician / Monitoring Project Implementation
Experience / engineering cost accountant)
Wu Yuezhen (Nanjing Maikang Network Technology Co., Ltd. / Sapphizer / Part-time Technician / Unmanage System Implementation
experience)
Li Guangping (Hefei WeClong Network Technology Co., Ltd. / Technician / Comprehensive Wiring Experience / Engineering Supervision
)
Chen Hao (Hefei WeClong Network Technology Co., Ltd. / Driver)
Sun Wei (Lu'an Telecom Industrial Co., Ltd. / Engineering Supervision)
Project Implementation Time: February 25, 2005 March 10, 2005
I am exhausted, my hands are ironed in the hands, my hand is cracking, my sleep is insufficient, but I have learned a lot ..
.