W05031 Summary

xiaoxiao2021-03-06  14

February 28, 2005 - March 5, 2005

According to the plan, this week's main goal is to complete demand development and implementation of preliminary design.

Although we can identify more than 80% of the needs, confirm that demand is still an essential link, and its purpose is mainly to eliminate our doubts about details in design. However, because the client has never been able to confirm the meeting in accordance with the plan, we can only select some high priority requirements, such as user management, authority management, etc.

This week I also corrected a wrong decision. It was originally arranged to give two new websites to two newcomers, but through two weeks observations, they did not seem to have independent work, because of the combination of work frustration Let them produce burnout and conflict emotions, and they still can't achieve the expected results after several training. I decided to adjust the strategy, the task is arranged unchanged, but I will no longer explain the so-called system design ideas and philosophy, change to the specific design example, how to export from business needs, and get specific classes and data based on design guidelines Table, while letting them put their own questions at all stages, tactically explain, feel good, at least this time they seem to have something you should do. I feel from this matter that communication is sometimes difficult. The door, Xuan Zhi is also a mysterious. I decided to take this effective way to take a practical road.

The construction of other systems is still in accordance with the plan, but it has been lagging behind. What is more worried about B, in fact, we don't have a strong design ability. According to the plan, you will start to do architecture design next week, but in my opinion, it may be a bit. How can I make a good design if there is no profound understanding and understanding of JSF, Spring, Ibatis. What is more worried about, although I have repeatedly introduced the concepts of the software process, it seems to be minored, everyone's work seems to have no plan, it seems that I have to ensure the implementation of the plan, and let everyone Understand the standards and objectives of each task.

In addition, in business, considering that we are an unspervious team, this has brought huge risks to the project. In order to ensure the completion of the contract, we decided to postpone the contract of the contract (because the contract is contracting from the contract Delivered within 100 days of days) until the client can take the time to cooperate with our needs.