February 16-2, 2005 - February 18, 2005, the contract has not been signed, and some details are talking about it, so the planned confirmation and the project leadership team have no way. From February 21, 2005, on February 26, 2005, this week's main task is to open the demand special meeting and confirm the demand for A package, and there is also no way to implement. Cause: Customer unit party members are driving the party members "Wait" Learning, like this hall level unit, is not almost impossible for party members. Plus, the meeting is more than the beginning of the year, so there is no empty. After many contacts, basically determined that next two weeks, I will give us four mornings. It is actually more worrying about it. The project team members have never done Java projects, but we have reserved nearly 3 months for this project, so far, only one person makes me rest assured. In addition, no need for demand and design, no one can help me (a little depressed), I only hope that they can carefully look at my needs and architecture design, take the initiative to ask questions, don't meet every item, I will talk about me. No one is involved in discussions. In addition, from this week, members of the project team overtime will be three consecutive months. At the same time, in order to ensure the control of the project progress, each member is required to fill in the weekly work plan summary table according to the project development plan. BTW, although the contract is still no sign, the problem has been done, an accident has disappeared automatically, huh, huh.