Look at Microsoft's MSF, risk management is always placed on a high position. In fact, the risk management of MSF summarizes six words, and it is not difficult to implement. (People write these six words into a book, I also took jolt, that is what people are ")
Which word is these words? It is active, formal, accumulated.
Take the initiative: Willing to face the problem, you are looking for yourself. Otherwise, risk management is always only on the side.
Formal: Official risk management is to fill in FORM. Otherwise, I want to have a risk management in my heart.
1. List all the potential risks and harm levels, the estimate of the probability,
Through the level of harm *, the probability = risk exposure rate, the top 10 of the top 10 in the exposure rate is discharged.
2. Develop risk control programs, how to control, transfer, who is responsible for controlling this risk.
3. Constantly looping, control, and eliminate 10 risks.
Accumulation: Constant accumulation of possible potential risks and controlled exclusion methods, which is almost the largest risks in risk management. Otherwise, every project takes a head thinking about what risks, and then I want to solve it.
It can be seen that risk management can help avoid the current project's risk, and achieve the growth of the entire organization through the accumulation of the risk plan. Even if you advocate Agile's PM, risk management is also a must-have for the viewing, home travel.