I know my lower level unable to withstand my superiors, re-establish a good plan, put human resources, and start fighting.
The first week: there is almost no progress, because most people need to be familiar with the second week of business knowledge and development environment: according to the progress requirements, it is still lagging 3 days (this is the result of everyone overtime), and after discussing the project, I immediately Decided to drag the legs one of the legs, supplement two programmers on the third week of the third week: 1 day, the supplement is very timely fourth week: According to the report, it has been chasing progress, but the project leader is very careful, BUG number may More than expected, the superior issuance, I want progress, referring to the progress of quality assurance! The fifth week: BUG has not been changed, the person is about to retreat. The project leader decided to revise the bug after leaving others. Tail
I can only say that we are about to pay for the starting thing.